  1. 15-year contract, with Commencement Date: September, 2013
  2. Supply water to 1.2 million people (population served)
  3. Number of customers: about 100,000 active customers, this number is expected to double within 4 years
  4. 21 Km mains pipelines > 1500 mm
  5. Length of Existing Distribution Network about 780 Km
  6. 5 Main Underground Reservoirs (UGR)
  7. About 40 small capacity UGRs at booster pumping stations
  8. One Water Treatment Plant at Nangloi (current capacity 40 MGD)
  9. About 43 booster stations
Project Objectives
  1. Enhance Service Standard
  2. Reduction in Non – Revenue Water (NRW)
  3. Energy Conservation
  4. Improved water quality
  5. Extension of water supply in un-served areas
  6.  Socio Economic improvements of the life quality standard in terms of hygiene and sanitation in the long term